Texas Governor Halts Data Center Grid Queue, Orders Subsidy Audit

What's documented Cites Gov. Greg Abbott's Aug. 3 letter to ERCOT and the PUCT, linked to the original PDF, plus ERCOT's own market notice delaying its review process.

Texas Gov. Greg Abbott ordered an audit of every data center in ERCOT's interconnection queue, which totals an estimated 474 GW, more than five times the state's record peak demand. ERCOT responded by delaying its Batch Zero transmission planning study, and the audit will examine which data center projects are paying their own way versus leaning on state tax incentives, grants or other public financial assistance.

Read the original at Utility Dive →
Share on LinkedIn Share on X Email