Georgia Regulators Scrutinize Secret OpenAI Power Deal

What's documented PSC committee meeting quotes from commissioners Johnson and Hubbard, an on-record staff review deadline (Aug. 26), and the redacted contract filing.

Georgia Power's contract to supply 3,200 MW to OpenAI's proposed $20 billion Project Camellia data center near Savannah is under Public Service Commission staff review, with staff signaling they would object unless Georgia Power changes contract terms. Democratic commissioners questioned whether existing large-load rules adequately protect residential ratepayers if the contract is terminated early or costs shift.

Read the original at The Atlanta Journal-Constitution →