Savannah Issues 155-Day Data Center Moratorium
What's documented Sourced to Savannah's unanimous city council vote and on-record remarks from Mayor Van Johnson, reported through a partnership with GPB News.
Savannah's city council unanimously passed a 155-day moratorium on large-load data centers over 10 megawatts and on converting warehouses larger than 200,000 square feet into data centers, joining roughly 40 other Georgia municipalities that have paused projects. The pause gives city staff time to assess what the facilities would demand from Savannah's water supply and power grid before any large-load applications are filed. A larger data center has already approached the city, and a smaller one under 25,000 square feet has a permit pending.
- Moratorium blocks large-load data centers over 10 MW and warehouse-to-data-center conversions above 200,000 square feet for 155 days.
- Savannah is roughly the 40th Georgia municipality to impose some form of data center moratorium.
- City staff will use the pause to evaluate water and energy grid capacity before large-load applications can be filed.
- A larger data center project has already approached the city; a sub-25,000-square-foot facility has a permit pending.